The Power Sector

Overview

Angola currently has approximately500 MW of generating capacity. The electricity sector in Angola comes under the Ministry of Energy and Water. The public utility in charge of electricity generation and transmission is ENE (Empresa Nacional de Electricidade). ENE is also responsible for the supply to the main urban centres, excepting Luanda, where distribution is the responsibility of EDEL (Empresa de Electricidade de Luanda).

Significant portions of the power generation and transmission systems have suffered serious damage as a result of the long war. In consequence there is, outside Luanda, only local generation and no distribution network

Electric current in Angola is 220 volts, 50 cycle. Voltage regulators and surge protectors are vital to protect expensive electronic equipment. Power outages and surges are frequent and overall there is an acute shortage of electricity in the country - about 15% of Angola's population have access to electric power.

After years of war and decay, several large projects are planned to boost the generating and distribution capacity of the country. The rehabilitation of the Luanda distribution system has already started.

Electricity consumption has also been severely constrained by the war. In spite of the booming population growth in Luanda (estimated at more than 4 million people), the growth in electricity demand has been less than 2 percent on an annual basis. This results from a combination of  the near total collapse of industrial activity, reportedly presently working at around 10 percent of its nominal capacity, and the fact that the vast majority of the population has only very limited need for electricity as some 75% of Angolans subsist on less than $1 per day.

The current suppliers of equipment for energy projects are Portugal, Spain, Brazil, France, Belgium, Sweden, USA, South Africa, Germany, Namibia and Norway.

 

Generation

The Angolan power generation systems consist of three separate systems and some small isolated ones. The North system covers Luanda and the provinces of Bengo, Malanje, Kwanza Norte and Kwanza Sul. The Centre system covers the provinces of Benguela and Huambo and the South system covers the provinces of Huila and Namibe.

ENE charges EDEL 3.6 cents/kWh.

 

Hydro

Angola is blessed with significant hydro resources. But, as with all of the nation's infrastructure, the hydro sector has been severely damaged or neglected during the war.

Angola plans to spend more than US$500 million over the next 20 years on building and restoring power facilities.

Some US$200 million will be spent on dam rehabilitation. The country has 5 main dams. At present only three of these are functional - Cambambe is operating at full potential but, Biopo and Matala are not. Cambambe was allocated US$70 million and has been fully rehabilitated. Biopo and Matala will receive US$3 million and US$20 million respectively. The remaining hydro plants, Mabubas and Lomaum, which were badly damaged during the war, will receive the remainder of the funds.

The construction of a massive new 520 MW power station at Capanda on the Cuanza River is underway, with the assistance of Brazilian and Russian contractors. Seven further hydro plants, with a total installed capacity of 16,505 MW, are planned on the Kwanza, Longa, Queve-Catumbela, Cunene and Cubango rivers.

A hydroelectric plant, a Joint Venture project with ENE, on the Chicapa river has been proposed by Alrosa, a Russian diamond company, to power its proposed US$40 million investment.

 

SUMMARY OF HYDRO CAPACITY.

Scheme            Location            River        Nº of Groups      Installed Power (MW)      Present Situation                                   

Capanda          Malanje           Kwanza               4                                520                         Construction in progress

Cambambe      K.Norte           Kwanza               4                                 180                        Operational-for rehabilitation

Matala               Huila              Cunene               3                                40.8                        2 operational in rehabilitation

Lomaum          Benguela         Catumbela          3                                 35                          Not operational-for rehabilitation

Mabubas         Bengo               Dande              4                                17.8                         Not operational-for rehabilitation

Biópio            Benguela          Catumbela         4                                14.4                         3operational in rehabilitation

Chicapa           L. Sul                 Chicapa           4                                 20                          About to be built

Source: ENE                                                  

In 2001, hydropower generation represented 62% (1.017 GWh) of ENE total power generation.

 

Thermal

Given the damage done to the hydro generating capacity, thermal power generation has become an important alternative source of generation. Most local governments outside Luanda, rely on diesel generators. Luanda has significant thermal generating capacity and oil companies rely heavily on it for their activities.

Appendix A gives details of thermal generating installations.

 

Transmission

The lack of capacity of the distribution network is due to natural ageing of the equipment, its poor maintenance and lack of investment, as well as the effects of war. As a consequence, the supply is unstable and coverage very poor.

The northern transmission network is limited to the 220 kV line linking the Cambambe dam to Luanda and the 60KV line from Luanda to Kifangondo. The former was built in

1963  and  designed  for a maximum 200 MW active power transit. It is operating under precarious conditions, as a result of sabotage and lack of maintenance during the war. Frequent interruptions occur in the supply of the Luanda region, amounting to some 500 to 600 hours per year on average.

A second 220 kV line was built in 1984 linking Cambambe and Luanda via Viana, also with a 200 MW maximum transit capacity. Unfortunately, this line has almost never been in operation and was completely destroyed by sabotage in the late 1980s. Two other HV transmission lines connect Cambambe respectively to the eastern cities of Ndalatando and Malanje and to Gabela and Sumbe in the south. They have also been partly destroyed several times and have been out of order since 1993.

EDEL consumes some 1000 Gwatts per annum with electricity rate losses of 15%, a market of 106.200 recorded consumers and monthly revenues of US$1 million.

Angola plans to spend more than US$300 million over the next 20 years on building and rehabilitating power lines. Details of current lines are at Appendix B.

 

Substations

Luanda has two substations. That at Viana is only partially in service due to sabotage. It is served by two 220 kV lines, one coming from Cazenga and other from Cambambe. Cambambe dam, together with five thermal stations, feeds the Cazenga substation.

 

None of the substations outside Luanda are fully operational and many require complete rehabilitation. Details of substations throughout Angola are at Appendix C.

 

Prospects

As is clear from the above, there is a vast amount of work needed to bring Angola's generating and distribution capacity up to a level that can meet its current needs.

After 40+ years of war, Angola is rightly looking to make use of its enormous potential, whether in oil, minerals, agriculture or the manufacturing industries which add value to those natural resources. If this is to happen, it will require much more than simply reinstating the current capacity. In addition, the Angolan people will be looking to enter a more normal, and hopefully, prosperous phase. This could mean a significant increase in the demand for domestic electricity supply.

According to ENE, the total rehabilitation of the entire electricity system requires an estimated investment of about US$1billion, of which US$334 million is for generation,

US$236 million for transmission and US$75 million for  substations . Details of investment plans are at Appendix D.

 

APPENDICES

Appendix A: Angola Thermal Power Generation

Scheme                         Unit Type                Power(MW)           Present Situation 

LUANDA
Group 1     
                 Gas Turbine                   24,4                           operational
Group 2          
            Gas Turbine                   28.8                           operational

Group 4      
                Gas Turbine                   24.5                           operational

Group 5 
                     Gas Turbine                   24.5                           operational

P.do Bispo     
                 Diesel                      20x1,2                          18 are operational

Congolenses 
                 Diesel                      5x1 ,46                        operational

Quartéis  
                        Diesel                      10x1,2                          6 operational
 

CABINDA
GTG Malongo
          Gas Turbine                     10                            Capital revision

Malon.Wakesha      Gas Turbine   
               5x2,2                          operational

Kholer S/E 
                    Diesel                        5x1,2                          operational

Caterpillar S/E
               Diesel                      2x1 ,4+1,0                Not operational

K.SUL
Caterp. P .Amboim
      Diesel                        2x1,5                           operational

Perkins Gabela
             Diesel                       2xO,2                           operational

Caterp. 
Peskuanza        Diesel                        3x1,5                       Not operational
Kholer Sumbe               Diesel                        2x1,5                        1 operational
Caterpillar Sumbe
        Diesel                        2x1,5                        1 operational

MALANJE
Perkins
                          Diesel                        1x1,0                        Being repaired

Caterpillar 
                                                      2x0,72                          Operational

Caterpillar 
                                                      1x1,0                            Operational


UIGE
Cent,P. FGW
              Diesel                        2x1,0                        Not operational

Disp. Kholer
                Diesel                      1x0,36                       Not Operational

MTU
                                                               1x1                               Operational
Disp.Kholer                                                    1x1                               Operational

LUNDA S.
CT Saurimo                Diesel                       1x2,8                         Capital revision 

BENGUELA
GTG Biópio           Gas Turbine                1x22,8                        Capital revision
CT Lobito (6PA6)      
Diesel                       4x5                            3 operational
CT Lobito  MTU         Diesel  
                  8x1,2                           5 operational

Cummins   
                   Diesel                    4 x1,1                            Not available

C Cavaco   
                  Diesel                    2x1,250                         Not available

HUAMBO
GTG   
                      Gas Turbine                  10                           Not operational

CAT  
                          Diesel                     3x1,2                             operational

CAT  
                          Diesel                     1x0,8                             operational

CUMMINS  
              Diesel                     1x0,8                              operational

CUMMINS 
               Diesel                     1x1,6                         Not operational

CAT Caala
                 Diesel                     1 x0,4                            operational

BIÉ
Diesel PT-1
                Diesel                    1x0,48                        Not operational

CT Kuito 
                   Diesel                  1 x1 ,48                           operational

Perkins
                       Diesel                     1x1                                operational

Caterpillar
                  Diesel                     1x1                                operational

NAMIBE
CT Xitoto                  Diesel                     2x5,6

Diesel Tômbwa
       Diesel                     2x1,2

6PA4 Tômbwa
        Diesel                     1x0,56

HUÍLA
CT Lubango MTU   Diesel                     6x1,2


MOXICO
CT Moxico
                Diesel                     1x1,0                          Being installed

Guascor
                    Diesel                    1x0,56                          Being repaired
 

 

Appendix B: Angola's Main Transmission Lines

From                              To                             Tension KV                  Length Kms                  Present Situation

CAPANDA         CAMBAMBE                         220                                                                     Installation in Progress
CAPANDA    
         CACUSO                             220                                                                     Installation in
Progress
CAMBAMBE       LUANDA-I                           220                                 176                              operational
CAMBAMBE    VIANA-LUANDA-II              220                                 175                             operational            
LUANDA                 VIANA                               220                                  18                              operational

VIANA                      BELAS                                60                                   35                              operational
LUANDA (CAZ)   CUCA (EDEL)                      60                                    4                               operational
LUANDA            KIFANGONDO                       60                                  30                               operational
CAMBAMBE           GABELA                          220                                 125                               Not operational
CAMBAMBE      NDALATANDO                 220                                   73                                operational

NDALATANDO        CACUSO                       100                                   93                               Not operational

CACUSO   
                MALANGE                     100                                   66                               Not operational

MABUBAS    
           LUANDA-I                      60                                  56.5                              Not operational

MABUBAS  
             LUANDA-II                    60                                  56.5                               Not operational

MABUBAS  
             KIFANGON                    60                                    27                                Not operational


MABUBAS    
             ÚCUA                            60                                   55                                 Not operational

ÚCUA
                           PIRI                               60                                   30                                 Not operational

PIRI 
                        QUIBAXE                           60                                   17                                  Not operational
GABELA                  SUMBE                             60                                   75                                 operational
GABELA              CACHOEIRAS                     60                                  38                                  Not operational

CACHOEIRAS          SUMBE                           60                                  37                                  operational
CACHOEIRA         P.AMBOIM                       60                                  35                                  Not operational
BIÓPIO                       KILEVA                        150                                  20                                  operational
KILEVA                     LOBITO                         150                                  8                                    operational
LOBITO                CATUMBELA                   150                                  4                                   operational
BENGUELA            CAVACO                         150                                  5                                    operational

CATUMBELA       BENGUELA                     150                                 32                                   operational
BIÓPIO                     CATUMB.                      150                                 23                                   operational
CATUMBELA         CAVACO                        60                                  28                                   operational
BIÓPIO                    LOMAUM                       60                                 96.5                                 Not operational
LOMAUM           ALTO CATUM.                 60                                48.5                                  Not operational
ALTO CATUM.     
HUAMBO                       60                               118.5                                 Not operational

ALTO CATUM.         CUBAL  
                       60                                 25                                    Not operational

HUAMBO   
         CATCHIUNGO                   60                                 65                                    Not operational
CATCHIUNGO      CHINGUAR                      60                                 20                                    Not operational
MATALA               LUBANGO                     150                               168                                    operational
MATALA              QUIPUNGO                     150                                60                                     operational

MATALA   
               JAMBA                        60                                120                                    Not operational


JAMBA   
          TCHAMUTETE                   60                                  68                                     Not operational

LUBANGO    
        NAMIBE-I                        60                                 162                                    operational

LUBANGO  
          NAMIBE-II                       60                                 162                                   operational

NAMIBE    
            TOMBWA                       60                                  93                                    operational
NAMIBE               SACO-MAR                     60                                   9                                      operational
NAMIBE                 TOMBWA                      60                                  93                                     operational

NAMIBE  
             SACO-MAR                     60                                   9                                      operational



ISOLATED SYSTEMS

MALONGO           CABINDA                       60                                   20                                     operational
MALONGO           LANDANA                     60                                   18                                     operational

LUKIXE   
                   UIGE                            30                                   15                                 Not operational

CAMACUPA
         KUITO                           30                                   90                                 Not operational

LUKIXE   
                  UIGE                             30                                   15                                 Not operational

CAMACUPA  
        KUITO                           30                                   90                                 Not operational

 

Appendix C: Angolan Substation Distribution                                     

Substation              Nº Units    Nominal Tension(Kv)      Triphase Nominal Power (MVA)       Present Situation
                                                    PRIM.  SEC.  TERC.                  PRIM.  SEC.  TERC.                                                    
LUANDA                       3            220      60       15                         60        50                                        Operational
NDALATANDO         1x3          220    100.5  31.5                        35        25                                         Operational

GABELA    
                    1            220     60       15                           35       25                                    Not operational

CAMBAMBE
               1            220     31.5                                  10       10                                         Operational

CACUSO     
                   2            100     31.5                                   5         5         6                           Not operational

MALANGE                    2            100     31.5                                   5         5         6                           Not operational
LUANDA                       2            63       11.5                                  33       33                                         Operational
LUANDA                       4            63       11.5                                  38       38                                         Operational

VIANA    
                       5            60        30                                    10       10                                     Not operational

KIFANGONDO   
          2            60       31.5                                  7.5      7.5                                    Not operational


MABUBAS    
                         6.6       60                                    74       7.4                                     Not operational

MABUBAS   
                2            6.6       60                                   3.7       3.7                                     Not operational

LOMAUM   
                 2             10      150                                  12.5    12.5                                    Not operational

LOMAUM    
                1             10      150                                 18.75   18.75                                  Not operational

BIOPIO   
                       1            150      10                                    28.5    28.5                                       Operational


BIOPIO 
                         1            150      60                                     15        15                                        Operational

A
. CATUMBELA        2            150      30     6                              10        6          6                           Not operational

HUAMBO  
                   2           150      30    6.6                            10        6          6                            Not operational

QUILEVA    
                  2           150      30                                    30        30                                          Operational

BIOPIO     
                     4            6         60                                    4.5       4.5                                          Operational

CATUMBELA     
       5           60        30                                    4.5       4.5                                          Operational


HUAMBO    
                2            6         30                                                                                           Not operational
HUAMBO                    1            6         30                                                                                           Not operational
LOBITO                        2           30        20                                     7.5       7.5                                        Operational
BENGUELA                 4           30        20                                     1.5       1.5                                        Operational
LOBITO                        4          30        10                                       5          5                                          Operational
JAMBA                        1         150       60    6.3                             20        10        10                        Not operational

LUBANGO                   1         150       60    15                              20        10        10                            Operational
MATALA                    2         150      10                                       17        17                                        Operational

NAMIBE   
                   1          60        15                                      10        10                                        Operational

NAMIBE    
                  1          60        15                                        5          5                                        Operational

NAMIBE   
                   2          60        15                                      15        6.3                                       Operational

SACO
                          1          60        6                                          4          4                                    Not operational


TCHAMUTETE          1          60        6.6                
                       5          5                                   Not operational

TOMBWA   
                2          60        15                                        5          5                                        Operational
 



Substations –Isolated Systems

Substation              Nº Units    Nominal Tension(Kv)      Triphase Nominal Power (MVA)       Present Situation
                                                    PRIM.  SEC.  TERC.                  PRIM.  SEC.  TERC.                                                    

UIGE 
                                1          100      30                                      10        10                                     Not operational

MALONGO  
                   3          30        0.04                                 1.895   1.895                                       Operational

CABINDA   
                    2          30        15                                        2          2                                          Operational

LANDANA   
                 1          6          30                                      0.5       0.5                                         Operational

LUENA     
                        1                                                                                                                     Not operational

BIE
                                     1                                                                                                                    Not operational
 

 

Appendix D: Investment Plans

DOMAIN             SYSTEM                DESIGNATION                                                                             INVESTMENT ( IN MlLLIONS USD)
                                                                                                                                                
YEAR l      YEAR 2      YEAR 3     YEAR 4      YEAR 5     TOTAL
PRODUCTION          NORTH        
 CAMBAMBEHYDROPOWER                                                    36.7          34.7             7.9                                              79.3
                                NORTH          CAMBAMBE HYDROPOWER(EMERGENCY INTERVENTION)     3              5                                                                    8                                     NORTH          MABUBAS DAM                                                                      18.1          13.1            3.5                                                34.7                                         NORTH          THERMAL CENTRE REHABILITATlON (GTG                            9